371 Dust suppression on road from Sarai singar chowk towards Baloda, Ch. 1630 towards Tiwarta side via Batari junction and Thana chowk junction towards Saraisingar chowk at Dipka expansion project of Dipka Area
372 Laying hume pipe culvert at different locations of nallah at Dipka expansion project of Dipka Area.
TRN : 770508 |  Korba - Chhattisgarh
Contract Value : 59.27 Lacs | Agency Name : South Eastern Coalfields Limited
Tender award for laying hume pipe culvert at different locations of nallah at dipka expansion project of dipka area.
373 Erection of lighting line pole from Excavation workshop no 3 for ensuring power and illumination to new site allocated for coal stocking behind canteen no. 3, KOCP
374 Repairing and strengthening of road from Balgi barrier to Regional workshop of SRK-Balgi Sub area of Korba area.
TRN : 769989 |  Korba - Chhattisgarh
Contract Value : 34.36 Lacs | Agency Name : South Eastern Coalfields Limited
Tender award for repairing and strengthening of road from balgi barrier to regional workshop of srk-balgi sub area of korba area.
375 Hiring of 01 no. 07 seats capacity non-AC LMV (Mahindra Bolero/Mahindra Scorpio/Mahindra Xylo or equivalent) on rental basis, with sufficient drivers for a period of 1095 day (03 years) for CMO, Banki and Surakachhar Hospital of Korba Area of SECL.
376 Civil works in RCPs and MOVs under PRRPL, Korba - Group B NOTE: 1. Please enable macros before filling the rates to see the quoted figures in words. 2. The bidder shall quote firm prices “Excess(+)/ At Par/ Less(-)” against the rates mentioned in the price schedule provided in BoQ1 sheet as per instructions provided herein after taking into account all the tender terms and conditions and scope of work. In case rates are quoted to more than 2 decimal places then, the amount quoted towards the tender shall be worked out for the rates quoted to first 2 decimal points without rounding off. 3. Only ""Bidder Name"", ""Excess (+) or ""At Par"" or Less (-)"" & ""Percentage"" are to be filled by the bidder in the designated ""Sky Blue cells"". For ""At Par"" selection, the percentage quoted shall be treated as 0.00 and quoted amount at par with estimate. 4. ""Excess (+)"" or ""At Par"" or ""Less (-)"" can be selected from the dropdown menu by clicking on the cell. 5. No changes shall be made by the bidder to S.No., Unit, Quantity. 6. In case of any difference in item description/unit/quantity in BOQ, then the item description/quantity/unit given in the tender document shall prevail. 7.The rates quoted by the tenderer shall include all cost towards equipment, labour & laboratory back-up, logistics, transport, spares, tools, tackles, consumables, etc., travel and stay arrangements and other incidentals including supply of materials as may be necessary for rendering the services as per detailed specifications. 8. Goods and Services tax as per GST Act 2017 for concerned services has been added to the base price of below mentioned services. If the bidder wishes to quote some other Goods and Services tax rate other than mentioned in the price schedule provided in BoQ1 sheet, they may quote the same in ""Annexure H-2 - Exceptions and Deviations"". Statutory variation on Goods and Services Tax as applicable for the category/service shall be to Owner’s account up to the contractual completion period. Reverse charges mechanism on Goods and Services tax amount shall be applicable as per Govt. rules. 9. Bidders are advised strictly not to alter or change the BOQ format/ contents. Bidders are also advised not to paste any image file or put any additional conditions in the BOQ work sheet. Abbreviations: Unit: CUM - Cubic Meter, SQM - Square Meter, M - Meter, FT2 - Square Feet, TO - Ton
TRN : 843447 |  Korba - Chhattisgarh
Contract Value : 77.90 Lacs | Agency Name : Indian Oil Corporation Limited
Tender award for civil works in rcps and movs under prrpl, korba - group b note: 1. please enable macros before filling the rates to see the quoted figures in words. 2. the bidder shall quote firm prices “excess(+)/ at par/ less(-)” against the rates mentioned in the price schedule provided in boq1 sheet as per instructions provided herein after taking into account all the tender terms and conditions and scope of work. in case rates are quoted to more than 2 decimal places then, the amount quoted towards the tender shall be worked out for the rates quoted to first 2 decimal points without rounding off. 3. only ""bidder name"", ""excess (+) or ""at par"" or less (-)"" & ""percentage"" are to be filled by the bidder in the designated ""sky blue cells"". for ""at par"" selection, the percentage quoted shall be treated as 0.00 and quoted amount at par with estimate. 4. ""excess (+)"" or ""at par"" or ""less (-)"" can be selected from the dropdown menu by clicking on the cell. 5. no changes shall be made by the bidder to s.no., unit, quantity. 6. in case of any difference in item description/unit/quantity in boq, then the item description/quantity/unit given in the tender document shall prevail. 7.the rates quoted by the tenderer shall include all cost towards equipment, labour & laboratory back-up, logistics, transport, spares, tools, tackles, consumables, etc., travel and stay arrangements and other incidentals including supply of materials as may be necessary for rendering the services as per detailed specifications. 8. goods and services tax as per gst act 2017 for concerned services has been added to the base price of below mentioned services. if the bidder wishes to quote some other goods and services tax rate other than mentioned in the price schedule provided in boq1 sheet, they may quote the same in ""annexure h-2 - exceptions and deviations"". statutory variation on goods and services tax as applicable for the category/service shall be to owner’s account up to the contractual completion period. reverse charges mechanism on goods and services tax amount shall be applicable as per govt. rules. 9. bidders are advised strictly not to alter or change the boq format/ contents. bidders are also advised not to paste any image file or put any additional conditions in the boq work sheet. abbreviations: unit: cum - cubic meter, sqm - square meter, m - meter, ft2 - square feet, to - ton
377 Diversion of various surface and quarry feeders at different locations due to widening of Nala at Dipka Expansion Project.
TRN : 768615 |  Korba - Chhattisgarh
Contract Value : 8.87 Lacs | Agency Name : South Eastern Coalfields Limited
Tender award for diversion of various surface and quarry feeders at different locations due to widening of nala at dipka expansion project.
378 Civil works in Station Piping area under PRRPL, Korba - Group A NOTE: 1. Please enable macros before filling the rates to see the quoted figures in words. 2. The bidder shall quote firm prices “Excess(+)/ At Par/ Less(-)” against the rates mentioned in the price schedule provided in BoQ1 sheet as per instructions provided herein after taking into account all the tender terms and conditions and scope of work. In case rates are quoted to more than 2 decimal places then, the amount quoted towards the tender shall be worked out for the rates quoted to first 2 decimal points without rounding off. 3. Only ""Bidder Name"", ""Excess (+) or ""At Par"" or Less (-)"" & ""Percentage"" are to be filled by the bidder in the designated ""Sky Blue cells"". For ""At Par"" selection, the percentage quoted shall be treated as 0.00 and quoted amount at par with estimate. 4. ""Excess (+)"" or ""At Par"" or ""Less (-)"" can be selected from the dropdown menu by clicking on the cell. 5. No changes shall be made by the bidder to S.No., Unit, Quantity. 6. In case of any difference in item description/unit/quantity in BOQ, then the item description/quantity/unit given in the tender document shall prevail. 7.The rates quoted by the tenderer shall include all cost towards equipment, labour & laboratory back-up, logistics, transport, spares, tools, tackles, consumables, etc., travel and stay arrangements and other incidentals including supply of materials as may be necessary for rendering the services as per detailed specifications. 8. Goods and Services tax as per GST Act 2017 for concerned services has been added to the base price of below mentioned services. If the bidder wishes to quote some other Goods and Services tax rate other than mentioned in the price schedule provided in BoQ1 sheet, they may quote the same in ""Annexure H-2 - Exceptions and Deviations"". Statutory variation on Goods and Services Tax as applicable for the category/service shall be to Owner’s account up to the contractual completion period. Reverse charges mechanism on Goods and Services tax amount shall be applicable as per Govt. rules. 9. Bidders are advised strictly not to alter or change the BOQ format/ contents. Bidders are also advised not to paste any image file or put any additional conditions in the BOQ work sheet. Abbreviations: Unit: CUM - Cubic Meter, SQM - Square Meter
TRN : 843448 |  Korba - Chhattisgarh
Contract Value : 20.26 Lacs | Agency Name : Indian Oil Corporation Limited
Tender award for civil works in station piping area under prrpl, korba - group a note: 1. please enable macros before filling the rates to see the quoted figures in words. 2. the bidder shall quote firm prices “excess(+)/ at par/ less(-)” against the rates mentioned in the price schedule provided in boq1 sheet as per instructions provided herein after taking into account all the tender terms and conditions and scope of work. in case rates are quoted to more than 2 decimal places then, the amount quoted towards the tender shall be worked out for the rates quoted to first 2 decimal points without rounding off. 3. only ""bidder name"", ""excess (+) or ""at par"" or less (-)"" & ""percentage"" are to be filled by the bidder in the designated ""sky blue cells"". for ""at par"" selection, the percentage quoted shall be treated as 0.00 and quoted amount at par with estimate. 4. ""excess (+)"" or ""at par"" or ""less (-)"" can be selected from the dropdown menu by clicking on the cell. 5. no changes shall be made by the bidder to s.no., unit, quantity. 6. in case of any difference in item description/unit/quantity in boq, then the item description/quantity/unit given in the tender document shall prevail. 7.the rates quoted by the tenderer shall include all cost towards equipment, labour & laboratory back-up, logistics, transport, spares, tools, tackles, consumables, etc., travel and stay arrangements and other incidentals including supply of materials as may be necessary for rendering the services as per detailed specifications. 8. goods and services tax as per gst act 2017 for concerned services has been added to the base price of below mentioned services. if the bidder wishes to quote some other goods and services tax rate other than mentioned in the price schedule provided in boq1 sheet, they may quote the same in ""annexure h-2 - exceptions and deviations"". statutory variation on goods and services tax as applicable for the category/service shall be to owner’s account up to the contractual completion period. reverse charges mechanism on goods and services tax amount shall be applicable as per govt. rules. 9. bidders are advised strictly not to alter or change the boq format/ contents. bidders are also advised not to paste any image file or put any additional conditions in the boq work sheet. abbreviations: unit: cum - cubic meter, sqm - square meter
379 Hiring along with installation and maintenance of 102 nos Window Air Coolers at various locations of Kusmunda Project for a period of 04 months.
380 Supply, installation packing the open Area and commissioning 225 nos of window Air coolers on hire basis under TA(EnM), Kusmunda Area
TRN : 769317 |  Korba - Chhattisgarh
Contract Value : 8.26 Lacs | Agency Name : South Eastern Coalfields Limited
Tender award for supply, installation packing the open area and commissioning 225 nos of window air coolers on hire basis under ta(enm), kusmunda area