2832Widening, Improvements, Improvements to Riding Quality to Government Roads Widening of Pipe Culvert and Slab Culvert, Construction of Retaining Wall and up keeping the roads for a period of 60 months in Harur (H) C&M Sub Division (Package 63)
The Following works are involved in this package
1. Widening from Intermediate lane to Two lane and Improvements of Pappireddipatti - Morappur road (via) Pallipatti, Thenkaraikottai at km 28/480 - 29/6 including widening of pipe culvert at km 29/6 (MD 328 A) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1366)
2. Widening from single lane to intermediate lane and Improvements of Kambainallur - Irumathur road at km 1/6-2/2 & 5/4 - 5/6 and including construction of retaining wall at 1/8-2/0 and widening of pipe culvert at km 5/2. including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-2690)
3. Widening from single lane to intermediate lane and improvements of Kambainallur - Anandur road at Km 0/0 - 2/0 and widening of slab at km 0/6 including upkeeping for a period of 60 months (01-CRIDP-19-20-O-2704)
4. Improvements to Riding Quality at km 0/0 - 4/6 of Navalai - Peramandapatti road (Using plastic waste) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4616)
5. Improvements to Riding Quality at km 0/0 - 5/0 of Eachampadi - Thoddampatti road Nainagoundanpudur road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4615)
6. Improvements to Riding Quality at km 0/2 - 1/2 and 2/0 - 3/4 of Odasalpatti - Kambainallur road Kathirnaickanahalli Puliyampatti road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4612)
7. Construction Retaining wall at km 15/8-16/0 of Morappur - Marandahalli road (MD 271) (01-CRIDP-19-20-M-1398)"
TRN :
718795
|
Salem - Tamil Nadu
Contract Value :
5.93 Crore |Agency Name :
Highway Department
2834Widening, Strengthening, Improvements and Culvert including upkeeping works for 60 Months in Cuddalore (H) C&M Subdivision Jurisdiction (Package-63)
A-Widening from Two lane to Three lane and Strengthening of Cuddalore - Tirukoilur-Sankarapuram road at km 13/2-14/0 (SH-68) Including Upkeepingfor a period of 60 Months
B-Improvements of Sitharasur road at km 0/0-1/0 including Reconstruction of culvert at km Km 0/6, 0/10, (i), 0/10, (ii) (MD 585) Including Upkeepingfor a period of 60 Months
C-Improvements of Sitharasur road at km 1/0-2/4 including Reconstruction of culvert at km 1/6, 2/2 (MD 585) Including Upkeepingfor a period of 60 Months
D- Improvements of Sitharasur road at km 2/4 - 3/6 including Reconstruction of Box culvert at km 3/2 , 3/4 (MD 585) Including Upkeepingfor a period of 60 Months
E- Improvements of Sitharasur road at km 3/6 - 4/9 including Reconstruction of culvert at km 3/8 , 3/10 (MD 585) Including Upkeepingfor a period of 60 Months"
TRN :
679980
|
Villupuram - Tamil Nadu
Contract Value :
5.29 Crore |Agency Name :
Highway Department
2835Widening, Improvements, Realignment of curve, Construction of culvert, retaining wall including upkeeping in Katpadi (H) C&M Sub Division Jurisdiction
A)Widening from Two lane to Three lane and Improvements of Ponnai - Thiruvalam Road at km 12/8 - 14/0 (SH 124) including upkeeping for a period of 60 months.01-CRIDP-19-20-S-0129
B)Widening from Two lane to Three lane and Improvements of Ponnai - Thiruvalam Road at km 14/520 - 15/4 Widening Culvert at Km 14/6,14/8(ii) Reconstruction of culvert at
Km 14/8(i)(SH 124) including upkeeping for a period of 60 months.01-CRIDP-19-20-S-0130
C)Realignment of curves at km 14/0-14/300 of Ponnai - Thiruvalam Road including Construction of Retaining Wall at Km 14/100-14/300 (SH 124) 01-CRIDP-19-20-S-0140. D)Realignment of curves at km 14/300-14/520 of Ponnai - Thiruvalam Road including Construction of Retaining Wall at Km 14/3-14/475 (SH 124) 01-CRIDP-19-20-S-0141.
TRN :
721766
|
Chennai - Tamil Nadu
Contract Value :
5.85 Crore |Agency Name :
Highway Department
2836Widening, Improvements, Improvements to Riding Quality to Government Roads including Widening and Reconstruction of Culvert , Widening of RCC Slab Culvert and Pipe Culvert and up keeping the roads for a period of 60 months in Palacode (H) C&M Sub Division (Package 59)
The Following works are involved in this package
1. Widening from Single lane to Intermediate lane and Improvements of Marandahalli - Panchapalli road at km 4/0 - 5/8 and including Reconstruction of culvert at km 6/8 Widening of Culvert at Km 4/4, 4/10, 5/6 including upkeeping for a period of 60 months (01-CRIDP-19-20-O-2697)
2. Widening from Single lane to Intermediate lane and Improvements of Marandahalli - Panchapalli road at km 8/0 - 9/6 and including Reconstruction of culverts at km 8/8, 9/6 including upkeeping for a period of 60 months (01-CRIDP-19-20-O-2695)
3. Improvements to Riding Quality at km 0/0 - 4/0 of Kaduchettipatti - Panchapalli road including up keeping for a period of 60 months. (01-CRIDP-19-20-I-4627)
4. Widening from Single lane to Intermediate lane and Improvements of Marandahalli - Panchapalli road at km 5/8 - 7/0 and including Reconstruction of culvert at km 6/10 including upkeeping for a period of 60 months (01-CRIDP-19-20-O-2698)
5. Widening of RCC slab culvert at km 6/10, 7/2 of Palacode - Kesarkuli road including up keeping for a period of 60 months. (01-CRIDP-19-20-I-2719)
6. Widening of Pipe Culvert at km 2/4 of Palacode - Nagadasampatty road (SH 224) including upkeeping for a period of 60 months (01-CRIDP-19-20-O-0463)
7. Improvements to Riding Quality at km 0/0 - 0/4 and 0/6 - 1/0 of Palacode- Erumampatti road including up keeping for a period of 60 months. (01-CRIDP-19-20-S-4631)"
TRN :
723944
|
Salem - Tamil Nadu
Contract Value :
5.73 Crore |Agency Name :
Highway Department
2838Widening, Strengthening, Improvements and Culvert including upkeeping works for 60 Months in Cuddalore & Panruti (H) C&M Subdivision Jurisdiction (Package 69)
A- Widening from Two lane to Three lane and Strengthening of Cuddalore - Chittoor Road at km 22/0 - 22/4 and 22/6 - 22/8 including reconstruction of culvert at km 22/2 (SH9) including upkeeping for a period of 60 months
B-Strengthening of Cuddalore - Chittoor Road at km 24/2 - 24/900 (SH9) including upkeeping for a period of 60 months
C-Improvements of Anathur-Perangiyur road at km 7/8 - 8/8 including upkeeping for a period of 60 months
D-Widening from Two lane to Three lane and Strengthening of Cuddalore - Thirukoilur - Sankarapuram road km 14/0-15/0 including upkeeping for a Period of 60 Month
E- Improvements of the Road from KM 11/8 of Cuddalore - Chittoor Road to Nellikuppam West Diversion road km 0/5-1/4 Including Reconstruction of culvert at km. 0/8,1/2 including upkeeping for a Period of 60 Month"
TRN :
679981
|
Villupuram - Tamil Nadu
Contract Value :
5.08 Crore |Agency Name :
Highway Department
2840Strengthening, Improvements and Improvements to Riding Quality to Government Roads including CD works and up keeping the roads for a period of 60 months in Krishnagiri (H) C&M Sub Division (Package 74)
The Following works are involved in this package
1. Strengthening of Sappanipatti - Panandhur - Bandarahalli road at km 0/0-2/0 Including CD works including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-2738)
2. Strengthening of Sappanipatti - Panandhur - Bandarahalli road at km 2/0-4/0 Including CD works including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-2739)
3. Improvements of Sokkadu - KRP Dam road at km 6/0-9/5 Including CD works including upkeeping for a period of 60 months.(01-CRIDP-19-20-O-2740)
4. Improvements of Kannampalli Temple road km 1/6-3/2 including Retaining wall including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-2741)
5. Improvements of Sappanipatti - Panandhur - Bandarahalli road at km 4/0-6/0 including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-A182742)
6. Improvements to Riding quality at km 0/0-3/0 of Sokkadu - KRP Dam road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4646)
7. Improvements to Riding quality at Km 0/0-2/0 of Kaveripattinam-Panagamutulu road including upkeeping for a period of 60 months. (01-CRIDP-19-20-I-4650)
8. Improvements to Riding quality at Km 0/0-2/4 of Sentharapalli-Nakkalpatti-Majeethgollahalli road including upkeeping for a period of 60 months. (01-CRIDP-19-20-I-4658)
9. Improvements to Riding quality at Km 1/6-5/4 of Vellampatti-Veramalai Road including upkeeping for a period of 60 months. (01-CRIDP-19-20-I-4663 )"
TRN :
723945
|
Salem - Tamil Nadu
Contract Value :
7.34 Crore |Agency Name :
Highway Department