You have searched for tamil-nadu in Awarded Tender Result. Click on any tender to view further details.
3121Widening and Improvements to Riding Quality, Widening of Culverts and Construction of Retaining Walls and including Upkeeping for a Period of 60 Months on Government Roads in Karur (Highways), C&M, Sub Division. Package No.17
A) Widening from Two lane to Three lane of Karur - Vangal Road at km 2/2 - 4/0 including widening of culvert at Km 2/8, 3/4(MD 772) including upkeeping for a period of 60 months
B) Widening from Two lane to Three lane of Karur - Vangal Road at km 4/0 - 6/0 (MD 772) including widening of culvert at Km 4/6 and including upkeeping for a period of 60 months
C) Widening from Two lane to Three lane of Karur - Vangal Road (MD 772) at km 6/0 - 7/0 including construction of Retaining wall at Km 6/6, 6/8,Widening of culvert at Km 6/8 and including upkeeping for a period of 60 months
D) Widening from Two lane to Three lane of Karur - Vangal Road at km 7/0 - 9/0 including Widening of culvert at Km 8/8 (MD 772) including upkeeping for a period of 60 months
E) Improvements to Riding Quality at km 1/0 - 2/0 and 3/6 - 4/0 of Manmangalam - Vangal Road (MD 867) including upkeeping for a period of 60 months"
TRN :
719169
|
Tirupur - Tamil Nadu
Contract Value :
6.74 Crore |Agency Name :
Highway Department
3122Widening and Improvements, Improvements to Riding Quality, Widening of Culverts, Construction of Retaining Wall and Including Upkeeping for Period of 60 Months on Government Roads in Karur (Highways), C&M, Sub Division. Package No.21
A) Improvements to Riding Quality at km 2/4 - 4/6 of Karur - Esanatham - Koombur - Viriyampatty Road (MD 606) including upkeeping for a period of 60 months
B) Improvements to Riding Quality at km 6/0 - 9/4 of Nerur - Thalavapalayam CC road including upkeeping for a period of 60 months
C) Improvements to Riding Quality at km 4/4 - 6/8 of Somur - Achamapuram (via) Thirumukkudalur road including upkeeping for a period of 60 months
D) Widening from Single lane to Intermediate lane and Improvements of Nagai - Gudalur - Mysore road to Km 221/6 to branching Andankoil Agraharam road (Road - A) at km 0/0 - 2/300 Including Widening of Culvert and Construction of Retaining Wall including upkeeping for a period of 60 months
E) Widening from Single lane to Intermediate lane and Improvements of Km 9/0 of Paramathy - Noyyal road to Athipalayam road at km 0/0 - 2/0 including upkeeping for a period of 60 months
F) Widening from Single lane to Intermediate lane and Improvements of Km 9/0 of Paramathy - Noyyal road to Athipalayam road at km 2/0 - 2/8 and 3/0 - 4/4 including upkeeping for a period of 60 months
G) Improvements to Riding Quality at km 6/0 - 8/6 of Punnam - Pugalur Road (MD 668) including upkeeping for a period of 60 months
H) Improvements to Riding Quality at km 0/0 - 2/2 and 3/8 - 4/6 of Punnam - Pugalur Road (MD 668) including upkeeping for a period of 60 months"
TRN :
720135
|
Tirupur - Tamil Nadu
Contract Value :
7.25 Crore |Agency Name :
Highway Department
3123Improvements to Riding Quality and Including Upkeeping for a Peroid of 60 Months on Government Roads in Karur (Highways), C&M, Sub Division. Package No.16
A) Improvements to Riding Quality at km 217/2 - 218/0 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
B) Improvements to Riding Quality at km 216/0 - 217/2 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
C) Improvements to Riding Quality at km 214/8 - 216/0 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
D) Improvements to Riding Quality at km 213/4 - 214/8 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
E) Improvements to Riding Quality at km 283/2 - 285/0 of Varanasi - Kanyakumari Road (Abandoned portion of NH7 at Thottakurichi and Karur) (SH 41) including upkeeping for a period of 60 months
F) Improvements to Riding Quality at km 0/0 - 0/6 of New Amaravathi road including upkeeping for a period of 60 months"
TRN :
719170
|
Tirupur - Tamil Nadu
Contract Value :
5.47 Crore |Agency Name :
Highway Department
3124Strengthening, Widening, Improvements, Improvements to Riding Quality to Government Roads including CD works and Protective works and up keeping the roads for a period of 60 months in Denkanikottai (H) C&M Sub Division (Package 71)
The Following works are involved in this package:
1. Widening from Single lane to Intermediate lane and Strengthening of Denkanikottai -Jawalagiri - Karnataka State limit road at km 9/4-10/8 including CD Works and Protective works including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-2725)
2.Widening from Single lane to Intermediate lane and Strengthening of Denkanikottai -Jawalagiri - Karnataka State limit road at km 10/8-12/4 including CD Works and Protective works including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-2726)
3.Improvements of Denkanikottai-Bettamugilalam Road at Km 14/6-19/0 including upkeeping for a period of 60 months. (01-CRIDP-19-20-O-2743)
4.Improvements to Riding Quality at Km 22/0-26/0 of Denkanikottai-Bettamugilalam Road. including upkeeping for a period of 60 months. (01-CRIDP-19-20-I-4656)
5.Improvements to Riding Quality at Km 12/0-13/2 and 26/0-28/0 of Denkanikottai-Bettamugilalam Road Using Plastic waste including upkeeping for a period of 60 months. (01-CRIDP-19-20-I-4664)
6.Improvements to Riding Quality at Km 0/0-2/8 of Bellampalli-Kempathpalli Road Using Plastic waste including upkeeping for a period of 60 months. (01-CRIDP-19-20-I-4665)
7.Construction Protective Wall in Tank Bund Portion at Km 2/8 & 2/10 of Denkanikottai -Jawalagiri - Karnataka State limit road (01-CRIDP-19-20-O-2757)"
TRN :
721774
|
Salem - Tamil Nadu
Contract Value :
7.48 Crore |Agency Name :
Highway Department
3125Widening and Improvements, Improvements to Riding Quality, Widening of Culverts, Construction of Retaining Wall and Including Upkeeping for Period of 60 Months on Government Roads in Karur (Highways), C&M, Sub Division. Package No.21
A) Improvements to Riding Quality at km 2/4 - 4/6 of Karur - Esanatham - Koombur - Viriyampatty Road (MD 606) including upkeeping for a period of 60 months
B) Improvements to Riding Quality at km 6/0 - 9/4 of Nerur - Thalavapalayam CC road including upkeeping for a period of 60 months
C) Improvements to Riding Quality at km 4/4 - 6/8 of Somur - Achamapuram (via) Thirumukkudalur road including upkeeping for a period of 60 months
D) Widening from Single lane to Intermediate lane and Improvements of Nagai - Gudalur - Mysore road to Km 221/6 to branching Andankoil Agraharam road (Road - A) at km 0/0 - 2/300 Including Widening of Culvert and Construction of Retaining Wall including upkeeping for a period of 60 months
E) Widening from Single lane to Intermediate lane and Improvements of Km 9/0 of Paramathy - Noyyal road to Athipalayam road at km 0/0 - 2/0 including upkeeping for a period of 60 months
F) Widening from Single lane to Intermediate lane and Improvements of Km 9/0 of Paramathy - Noyyal road to Athipalayam road at km 2/0 - 2/8 and 3/0 - 4/4 including upkeeping for a period of 60 months
G) Improvements to Riding Quality at km 6/0 - 8/6 of Punnam - Pugalur Road (MD 668) including upkeeping for a period of 60 months
H) Improvements to Riding Quality at km 0/0 - 2/2 and 3/8 - 4/6 of Punnam - Pugalur Road (MD 668) including upkeeping for a period of 60 months
TRN :
719165
|
Tirupur - Tamil Nadu
Contract Value :
7.25 Crore |Agency Name :
Highway Department
3126Widening and Improvements to Riding Quality, Widening of Culverts and Construction of Retaining Walls and including Upkeeping for a Period of 60 Months on Government Roads in Karur (Highways), C&M, Sub Division. Package No.17
A) Widening from Two lane to Three lane of Karur - Vangal Road at km 2/2 - 4/0 including widening of culvert at Km 2/8, 3/4(MD 772) including upkeeping for a period of 60 months
B) Widening from Two lane to Three lane of Karur - Vangal Road at km 4/0 - 6/0 (MD 772) including widening of culvert at Km 4/6 and including upkeeping for a period of 60 months
C) Widening from Two lane to Three lane of Karur - Vangal Road (MD 772) at km 6/0 - 7/0 including construction of Retaining wall at Km 6/6, 6/8,Widening of culvert at Km 6/8 and including upkeeping for a period of 60 months
D) Widening from Two lane to Three lane of Karur - Vangal Road at km 7/0 - 9/0 including Widening of culvert at Km 8/8 (MD 772) including upkeeping for a period of 60 months
E) Improvements to Riding Quality at km 1/0 - 2/0 and 3/6 - 4/0 of Manmangalam - Vangal Road (MD 867) including upkeeping for a period of 60 months"
TRN :
720147
|
Tirupur - Tamil Nadu
Contract Value :
6.74 Crore |Agency Name :
Highway Department
3127Improvements, Improvements to Riding Quality, Construction of Retaining Walls and Including Upkeeping for Period of 60 Months on Government Roads in Krishnarayapuram (Highways), C&M, Sub Division. Package No.26 Road A:- Improvements of Thogamalai - Mylmpatty road at Km.6/0-7/6 (MD 482) including upkeeping for a period of 60 months.
Road B:- Improvements of Manapparai – Gujiliamparai Road Km.18/450-22/0 (MD 628) including upkeeping for a period of 60 months.
Road C:- Improvements of Manapparai – Gujiliamparai Road Km.22/0-25/0 (MD 628) including upkeeping for a period of 60 months.
Road D:- Improvements to Riding Quality at Km.4/0-6/4 of Mylampatty – Palayam Road (MD 280) including upkeeping for a period of 60 months.
Road E:- Improvements of Manapparai - Gujiliamparai road Km.15/4-17/0 (MD 628) including upkeeping for a period of 60 months.
Road F:- Improvements to Riding Quality at Km.0/0-5/2 of Veeranampatty – Nalluranpatty Road including upkeeping for a period of 60 months.
Road G:- Construction of retaining wall at Km.0/8, 2/2, 3/2 & 3/4 of Servaikaranpatty - Thanivasal Road.
TRN :
719161
|
Tirupur - Tamil Nadu
Contract Value :
6.67 Crore |Agency Name :
Highway Department
3128Improvements to Riding Quality and Including Upkeeping for a Peroid of 60 Months on Government Roads in Karur (Highways), C&M, Sub Division. Package No.16
A) Improvements to Riding Quality at km 217/2 - 218/0 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
B) Improvements to Riding Quality at km 216/0 - 217/2 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
C) Improvements to Riding Quality at km 214/8 - 216/0 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
D) Improvements to Riding Quality at km 213/4 - 214/8 of Old NH 67 road Veerarackiyam to Sukkaliyur (via)Gandhigramam within the Karur town limit (SH 145) including upkeeping for a period of 60 months
E) Improvements to Riding Quality at km 283/2 - 285/0 of Varanasi - Kanyakumari Road (Abandoned portion of NH7 at Thottakurichi and Karur) (SH 41) including upkeeping for a period of 60 months
F) Improvements to Riding Quality at km 0/0 - 0/6 of New Amaravathi road including upkeeping for a period of 60 months"
TRN :
720149
|
Tirupur - Tamil Nadu
Contract Value :
5.47 Crore |Agency Name :
Highway Department
3129Widening and Improvements, Improvements, Improvements to Riding Quality, Widening of Culverts, Construction of Retaining Walls and Including Upkeeping for Period of 60 Months on Government Roads in Krishnarayapuram (Highways), C&M, Sub Division. Package No.25 Road A:- Widening from Two lane to Three lane and Improvements of Vaiyampatty - Karur road (via) Mylampatty - Uppidamangalam at Km 11/900-13/0 including widening of culvert at Km 12/2,12/4 & 12/6 (SH 199) including upkeeping for a period of 60 months.
Road B:- Improvement of Musiri - Kulithalai - Pudukottai - Alangudi - Peravoorani - Sethubhavachatram Road at Km.23/0-25/0 (SH 71) including upkeeping for a period of 60 months.
Road C:- Improvement of Musiri - Kulithalai - Pudukottai - Alangudi - Peravoorani - Sethubhavachatram Road at Km.25/0-26/0 (SH 71) including upkeeping for a period of 60 months.
Road D:- Improvements to Riding Quality at Km.9/0-12/4 of Palaviduthi - Kadavur - Ayyalur road (MD 648 ) including upkeeping for a period of 60 months.
Road E:- Construction of retaining wall at Km.19/2, 19/4, 19/6, 19/8, 19/10, 20/2, 20/6, 20/10, 22/8, 27/10, 28/2 & 29/6 of Manapparai - Gujiliyamparai road (MD 628)
Road F:- Improvements to Riding Quality at Km.0/0-2/0 of Veeranampatty – Viralipatty road including upkeeping for a period of 60 months
TRN :
719162
|
Tirupur - Tamil Nadu
Contract Value :
5.71 Crore |Agency Name :
Highway Department
3130Improvements to Riding Quality, Construction of Retaining Walls and Including Upkeeping for Period of 60 Months on Government Roads in Krishnarayapuram (Highways), C&M, Sub Division. Package No.26 Road A:- Improvements of Thogamalai - Mylmpatty road at Km.6/0-7/6 (MD 482) including upkeeping for a period of 60 months.
Road B:- Improvements of Manapparai – Gujiliamparai Road Km.18/450-22/0 (MD 628) including upkeeping for a period of 60 months.
Road C:- Improvements of Manapparai – Gujiliamparai Road Km.22/0-25/0 (MD 628) including upkeeping for a period of 60 months.
Road D:- Improvements to Riding Quality at Km.4/0-6/4 of Mylampatty – Palayam Road (MD 280) including upkeeping for a period of 60 months.
Road E:- Improvements of Manapparai - Gujiliamparai road Km.15/4-17/0 (MD 628) including upkeeping for a period of 60 months.
Road F:- Improvements to Riding Quality at Km.0/0-5/2 of Veeranampatty – Nalluranpatty Road including upkeeping for a period of 60 months.
Road G:- Construction of retaining wall at Km.0/8, 2/2, 3/2 & 3/4 of Servaikaranpatty - Thanivasal Road.
TRN :
720126
|
Tirupur - Tamil Nadu
Contract Value :
6.67 Crore |Agency Name :
Highway Department