You have searched for highway-department in Awarded Tender Result. Click on any tender to view further details.

301 Strengthening and Improvements to Government Roads including providing CC pavements and Construction of Retaining wall and Upkeeping for a period of 60 months in Senthamangalam (H) C&M Sub Division (Package-40) The Following works are involved in this package 1. Improvements of Mohanur - Namakkal - Sendamangalam - Rasipuram road at km 35/900 - 37/6 (SH 95) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0421) 2. Strengthening of Namakkal - Kananur road at km 23/0 - 24/8 (SH 161) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0423) 3. Improvements of Kolli Hills ghat road at km 20/0 - 22/0 including Providing CC Pavements and Construction of Parapets in Km 15/0 - 16/0 and 21/0-22/0(MD 181) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1333) 4. Construction of Retaining wall at km 24/0-24/4 of Namakkal - Kananur road (SH 161) (01-CRIDP-19-20-S-0446) 5. Construction of Retaining wall at km 13/4, 13/6, 13/10, 14/2, 19/6 and 19/8 of Valapurpirivu - Kulivalavu road (01-CRIDP-19-20- O-2688) 6. Construction of Retaining wall at km 0/10, 1/6, 1/8, 1/10, 2/10 and 3/2 of Solakadu - Kulivalavu road (01-CRIDP-19-20-P-3676) 7. Construction of Retaining wall at km 5/10, 6/2, 6/4, 6/8 and 6/10 of Solakadu - Kulivalavu road (01-CRIDP-19-20-P-3677)
302 Special repairs to Govt. Roads in respect of Thirumayam (H) C&M Sub division Road A, Special Repairs to Perumanadu - Konnaiyur road at Km 12/0-14/0 (MD827) Road B, Special Repairs to Perumanadu - Konnaiyur road at Km 16/0-17/0 (MD827) Road C, Special Repairs to Koppanapatti - Vegupatti road at Km 35/0-36/8.
303 Improvements and Improvements to Riding Quality to Government Roads including Construction of Retaining wall and Upkeeping for a period of 60 months in Senthamangalam (H) C&M Sub Division (Package-41) The Following works are involved in this package 1. Improvements of Mohanur - Namakkal - Sendamangalam - Rasipuram road at km 30/2 - 32/4 (SH 95) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0422) 2. Construction of RCC Retaining wall at km 3/4 of Nanjundapuram - Naducombai road (MD 293) (01-CRIDP-19-20-M-1354) 3. Improvements to Riding Quality at km 3/850 - 8/0 of Nanjundapuram - Naducombai road (MD 293) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4566) 4. Construction of RCC Retaining wall at km 3/2 of Nanjundapuram - Naducombai road (MD 293) (01-CRIDP-19-20-M-1351) 5. Construction of Retaining wall at km 3/6 & 3/8 of Nanjundapuram - Naducombai road (MD 293) (01-CRIDP-19-20-M-1352) 6. Construction of Retaining wall at km 5/8 and 5/10 of Nanjundapuram - Naducombai road (MD 293) (01-CRIDP-19-20-M-1353) 7. Improvements to Riding Quality at km 1/8 - 2/8 of Kulivalavu - Othakadai road including upkeeping for a period of 60 months. (01-CRIDP-19-20-I-4594) 8. Improvements to Riding Quality at km 1/0 - 3/6 of Thirumalaipatti - Eadayapatti - Veerampatti road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4588)
TRN : 721326 |  Salem - Tamil Nadu
Contract Value : 6.84 Crore | Agency Name : Highway Department
Tender award for improvements and improvements to riding quality to government roads including construction of retaining wall and upkeeping for a period of 60 months in senthamangalam (h) c&m sub division (package-41) the following works are involved in this package 1. improvements of mohanur - namakkal - sendamangalam - rasipuram road at km 30/2 - 32/4 (sh 95) including upkeeping for a period of 60 months (01-cridp-19-20-s-0422) 2. construction of rcc retaining wall at km 3/4 of nanjundapuram - naducombai road (md 293) (01-cridp-19-20-m-1354) 3. improvements to riding quality at km 3/850 - 8/0 of nanjundapuram - naducombai road (md 293) including upkeeping for a period of 60 months (01-cridp-19-20-i-4566) 4. construction of rcc retaining wall at km 3/2 of nanjundapuram - naducombai road (md 293) (01-cridp-19-20-m-1351) 5. construction of retaining wall at km 3/6 & 3/8 of nanjundapuram - naducombai road (md 293) (01-cridp-19-20-m-1352) 6. construction of retaining wall at km 5/8 and 5/10 of nanjundapuram - naducombai road (md 293) (01-cridp-19-20-m-1353) 7. improvements to riding quality at km 1/8 - 2/8 of kulivalavu - othakadai road including upkeeping for a period of 60 months. (01-cridp-19-20-i-4594) 8. improvements to riding quality at km 1/0 - 3/6 of thirumalaipatti - eadayapatti - veerampatti road including upkeeping for a period of 60 months (01-cridp-19-20-i-4588)
304 Strengthening, Improvements, Improvements to Riding Quality to Government Roads and up keeping the roads for a period of 60 months in Pappiredipatti (H) C&M Sub Division (Package 68) The Following works are involved in this package: The Following works are involved in this package 1. Strengthening of Mallapuram - Mookanur road at km 8/2 - 9/0 (MD 237) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1375) 2. Strengthening of Mallapuram - Mookanur road at km 9/0 - 10/0 (MD 237) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1376) 3. Improvements of Mallapuram - Mookanur road at km 10/0 - 11/0 and 12/0 - 12/300 (MD 237) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1368) 4. Strengthening of Mallapuram - Mookanur road at km 11/0 - 12/0 (MD 237) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1370) 5. Improvements to Riding Quality at km 13/0 - 16/0 of Mallapuram - Mookanur road (MD 237) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4601) 6. Improvements to Riding Quality at km 16/0 - 18/6 of Mallapuram - Mookanur road (MD 237) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4602)"
305 Widening, Improvements and Improvements to Riding Quality to Government Roads including Curve Improvements, Construction and Widening of Pipe Culverts, Construction of Drain and Well Protective wall and Upkeeping for a period of 60 months in Namakkal (H) C&M Sub Division (Package-37) The Following works are involved in this package 1. Improvements of Namakkal-Kananur road at km 4/300-4/8 (SH161) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0416) 2. Widening from Twolane to Threelane and Improvements of Mohanur-Namakkal - Sendamangalam-Rasipuram road at km15/0-15/700 and including Widening of pipe culvert at km.15/6 Curve improvements with Strom water drain at Km18/8 (SH95) including upkeeping for aperiod of 60 months (01-CRIDP-19-20-S-0410) 3. Construction of Well protecting wall at km 22/2 of Mohanur - Namakkal - Sendamangalam - Rasipuram road (SH 95) (01-CRIDP-19-20-S-0428) 4.Construction of Well protecting wall at km 6/2 of Pullagoundam patti - Serukkalai road (01-CRIDP-19-20-O-2654) 5. Construction of Well protecting wall at km 2/6 of Oruvandur Pudur - Kidaram road (01-CRIDP-19-20-O-2655) 6. Construction of Well protecting wall at km 2/8 of Vagurampatti - Veppanatham road (01-CRIDP-19-20-O-2656) 7. Construction of Well protecting wall at km 7/2 of Rayarpalayam - Karuchipalayam -Kolaram road and Construction of Pipe Culvert at Km 6/4 (01-CRIDP-19-20-O-2657) 8. Improvements to Riding Quality at km 6/4 - 8/6 of Rayarpalayam - Karuchipalayam - Kolaram road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4571) 9. Improvements to Riding Quality at km 2/4 - 3/0 and 5/0 - 6/6 of Namakkal - Nainamalai road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4572) 10. Improvements to Riding Quality at km 0/0 - 1/0 of Pudupatti - Kurumbapatti road (Using plastic waste) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4573) 11. Improvements to Riding Quality at km 0/0 - 3/4 of Oruvandur Pudur - Kidaram road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4574) 12. Improvements to Riding Quality at km 0/0 - 0/6 and 1/6 - 2/8 of Vagurampatti - Veppanatham road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4575) 13. Improvements to Riding Quality at km 0/0 - 2/4 of Alampatti union road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4576) 14. Construction of Retaining wall at km 14/10 of Vallipuram - Palapatti road (01-CRIDP-19-20-O-2678) 15. Construction Well protecting wall at km 2/4 of Namakkal - Nainamalai road (01-CRIDP-19-20-O-2668) 16 Construction Well protecting wall at km 3/6 of Vettambadi - Lakkamanaic kenpatti road (01-CRIDP-19-20-O-2669) 17. Construction Well protecting wall at km 3/8 of Lathuvadi - N.Pudupatti road (01-CRIDP-19-20-O-2670) 18. Construction Well protecting wall at km 1/8 of Veesanam Vettambadi road (01-CRIDP-19-20-O-2671)
TRN : 721333 |  Salem - Tamil Nadu
Contract Value : 5.09 Crore | Agency Name : Highway Department
Tender award for widening, improvements and improvements to riding quality to government roads including curve improvements, construction and widening of pipe culverts, construction of drain and well protective wall and upkeeping for a period of 60 months in namakkal (h) c&m sub division (package-37) the following works are involved in this package 1. improvements of namakkal-kananur road at km 4/300-4/8 (sh161) including upkeeping for a period of 60 months (01-cridp-19-20-s-0416) 2. widening from twolane to threelane and improvements of mohanur-namakkal - sendamangalam-rasipuram road at km15/0-15/700 and including widening of pipe culvert at km.15/6 curve improvements with strom water drain at km18/8 (sh95) including upkeeping for aperiod of 60 months (01-cridp-19-20-s-0410) 3. construction of well protecting wall at km 22/2 of mohanur - namakkal - sendamangalam - rasipuram road (sh 95) (01-cridp-19-20-s-0428) 4.construction of well protecting wall at km 6/2 of pullagoundam patti - serukkalai road (01-cridp-19-20-o-2654) 5. construction of well protecting wall at km 2/6 of oruvandur pudur - kidaram road (01-cridp-19-20-o-2655) 6. construction of well protecting wall at km 2/8 of vagurampatti - veppanatham road (01-cridp-19-20-o-2656) 7. construction of well protecting wall at km 7/2 of rayarpalayam - karuchipalayam -kolaram road and construction of pipe culvert at km 6/4 (01-cridp-19-20-o-2657) 8. improvements to riding quality at km 6/4 - 8/6 of rayarpalayam - karuchipalayam - kolaram road including upkeeping for a period of 60 months (01-cridp-19-20-i-4571) 9. improvements to riding quality at km 2/4 - 3/0 and 5/0 - 6/6 of namakkal - nainamalai road including upkeeping for a period of 60 months (01-cridp-19-20-i-4572) 10. improvements to riding quality at km 0/0 - 1/0 of pudupatti - kurumbapatti road (using plastic waste) including upkeeping for a period of 60 months (01-cridp-19-20-i-4573) 11. improvements to riding quality at km 0/0 - 3/4 of oruvandur pudur - kidaram road including upkeeping for a period of 60 months (01-cridp-19-20-i-4574) 12. improvements to riding quality at km 0/0 - 0/6 and 1/6 - 2/8 of vagurampatti - veppanatham road including upkeeping for a period of 60 months (01-cridp-19-20-i-4575) 13. improvements to riding quality at km 0/0 - 2/4 of alampatti union road including upkeeping for a period of 60 months (01-cridp-19-20-i-4576) 14. construction of retaining wall at km 14/10 of vallipuram - palapatti road (01-cridp-19-20-o-2678) 15. construction well protecting wall at km 2/4 of namakkal - nainamalai road (01-cridp-19-20-o-2668) 16 construction well protecting wall at km 3/6 of vettambadi - lakkamanaic kenpatti road (01-cridp-19-20-o-2669) 17. construction well protecting wall at km 3/8 of lathuvadi - n.pudupatti road (01-cridp-19-20-o-2670) 18. construction well protecting wall at km 1/8 of veesanam vettambadi road (01-cridp-19-20-o-2671)
306 Widening, Improvements and Improvements to Riding Quality to Government Roads including construction of Storm water Drain and Retaining wall and Upkeeping for a period of 60 months in Rasipuram (H) C&M Sub Division (Package-44) The Following works are involved in this package 1) Widening from Two Lane to Three Lane and Improvements of Rasipuram - Attur road at km 3/0 - 3/650 including Construction of Storm Water Drain (MD402) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1329) 2) Improvements of Attaiyampatti - Masakkalipatti road at km 3/2 - 5/4 (MD46) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1331) 3) Improvements of Attaiyampatti - Masakkalipatti road at km 11/6 - 12/8 (MD46) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1337) 4) Construction of Retaining wall at km 0/4, 0/6 and 1/10 of Km 9/4 of Attayampatti - Masakalipatti road to Olaipatti road (via) Palanthinnipatti (01-CRIDP-19-20-O-2680) 5) Improvements to Riding Quality at km 5/4-7/300 of Rasipuram Byepass road (MD) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4565) 6) Improvements to Riding Quality at km 4/0-7/6 of Seerapalli - Singalantha puram road (Using plastic waste) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4578) 7) Improvements to Riding Quality at km 0/0 - 1/2 of Rasipuram - Attur road to Oilpatti road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4592) "
TRN : 733478 |  Salem - Tamil Nadu
Contract Value : 5.57 Crore | Agency Name : Highway Department
Tender award for widening, improvements and improvements to riding quality to government roads including construction of storm water drain and retaining wall and upkeeping for a period of 60 months in rasipuram (h) c&m sub division (package-44) the following works are involved in this package 1) widening from two lane to three lane and improvements of rasipuram - attur road at km 3/0 - 3/650 including construction of storm water drain (md402) including upkeeping for a period of 60 months (01-cridp-19-20-m-1329) 2) improvements of attaiyampatti - masakkalipatti road at km 3/2 - 5/4 (md46) including upkeeping for a period of 60 months (01-cridp-19-20-m-1331) 3) improvements of attaiyampatti - masakkalipatti road at km 11/6 - 12/8 (md46) including upkeeping for a period of 60 months (01-cridp-19-20-m-1337) 4) construction of retaining wall at km 0/4, 0/6 and 1/10 of km 9/4 of attayampatti - masakalipatti road to olaipatti road (via) palanthinnipatti (01-cridp-19-20-o-2680) 5) improvements to riding quality at km 5/4-7/300 of rasipuram byepass road (md) including upkeeping for a period of 60 months (01-cridp-19-20-i-4565) 6) improvements to riding quality at km 4/0-7/6 of seerapalli - singalantha puram road (using plastic waste) including upkeeping for a period of 60 months (01-cridp-19-20-i-4578) 7) improvements to riding quality at km 0/0 - 1/2 of rasipuram - attur road to oilpatti road including upkeeping for a period of 60 months (01-cridp-19-20-i-4592) "
307 Strengthening, Improvements to Riding Quality, Construction of Retaining wall including up keeping for a period of 60 months in Govt. Roads in respect of Thiruthuraipoondi (H), C&M Subdivision Road A 01-CRIDP-19-20-S-0310 Strengthening of Thanjavur - Mannargudy - Thiruthuraipoondi - Vedaranyam - Kodiyakkari road at Km. 49/6 - 51/6 (SH63) including upkeeping for a period of 60 months Road B 01-CRIDP-19-20-S-0311 Strengthening of Thanjavur - Mannargudy - Thiruthuraipoondi - Vedaranyam - Kodiyakkari road at Km. 51/6 - 52/6 and 59/8 - 60/0 (SH63) including upkeeping for a period of 60 months Road C 01-CRIDP-19-20-S-0312 Strengthening of Mayiladuthurai - Thiruthuraipoondi Road at Km. 56/4 - 58/0 (SH23) including upkeeping for a period of 60 months Road D 01-CRIDP-19-20-I-4446 Improvements to Riding Quality at Km. 69/2 - 72/6 of Mayiladuthurai - Muthupet road (MD256) including upkeeping for a period of 60 months Road E 01-CRIDP-19-20-M-1286 Construction of Retaining wall at Km. 14/10 of Muthupet - Voimedu road (MD640) Road F 01-CRIDP-19-20-P-3666 Strengthening of Ovarur - Adithiravidar colony road at Km. 0/0 - 3/265 including upkeeping for a period of 60 months
308 Improvement Works including upkeeping in Vandavasi (H) C&M Sub Division Jurisdiction A) Improvements of Thellar - Senal - Nergunam Road to Pennattagaram Road at Km 0/0 - 2/2 including Upkeeping for a period of 60 months B) Improvements of Marudadu - Vepankaranai Road to Eramalur Road to Moodur at Km 0/0 - 3/5 including Upkeeping for a period of 60 months C) Improvements to Riding Quality at Km 0/0 - 3/8 of Vedal Road to Vadakkupattu Road (via) Magamayi, Thirumani including Upkeeping for a period of 60 months D) Improvements of Kottai - Badur Road at Km 6/0 - 8/0 including Upkeeping for a period of 60 months E) Improvements of Kottai - Badur Road at Km 8/0 - 10/2 including Upkeeping for a period of 60 months
309 PACKAGE-61 TIRUVARUR DIVISION CRIDP 2019-20
TRN : 744713 |  Trichy - Tamil Nadu
Contract Value : 5.90 Crore | Agency Name : Highway Department
Tender award for package-61 tiruvarur division cridp 2019-20
310 TIRUVARUR DIVISION CRIDP 2019-20.
TRN : 744714 |  Trichy - Tamil Nadu
Contract Value : 5.90 Crore | Agency Name : Highway Department
Tender award for tiruvarur division cridp 2019-20.