You have searched for tamil-nadu in Awarded Tender Result. Click on any tender to view further details.
3311Widening, Improvements, Curve Widening, Constructuion of Minor Bridge, Drain, Footpath, Junction Improvement works including
Upkeeping for a period of 60 months in Chennai City Roads & Tambaram (H) C&M Sub Division Jurisdiction
A)Construction Minor Bridge at Km 1 / 8 of Pallavaram -- Thiruneermalai -- Thirumudivakkam Road (MD 1163) ( 01 -- CRIDP -- 19 -- 20 -- O -- 0939)
B) Widening from Two lane to Four lane and Improvements of Tambaram - Somangalam - Nandambakkam Road at km 0/6 - 0/900 including Construction of Drain Cum
Footpath (MD1164) including upkeeping for a period of 60 months ( 01 -- CRIDP -- 19 -- 20 -- M -- 0934)
C) Improvements of Curve at Km 4 / 8 -- 5 / 2 Tambaram - Mudichur - Sriperumbudur Road (SH110) including Widening, junction Improvements and upkeeping for a period of 60 months ( 01 -- CRIDP -- 19 -- 20 -- S -- 0004)"
TRN :
676887
|
Chennai - Tamil Nadu
Contract Value :
5.09 Crore |Agency Name :
Highway Department
3312Widening, Improvements and Improvements to Riding Quality to Government Roads including Reconstruction of Culverts, Construction of Storm Water Drain, Retaining wall and providing Paver Blocks and Up keeping for a period of 60 months in Mettur (H) C&M Sub Division (Package-36)
The Following works are involved in this package
1) Improvements of Tholasampatty - Mallappanur road at Km.10/2-13/0 including Curve Widening at Km.12/2 and Construction of Retaining Wall at Km.11/2, 11/6 & 12/4 (MD1174A) including upkeeping for a period of 60 months 01-CRIDP-19-20-M-1320
2) Improvements to Riding Quality at Km.13/0-15/8 of Tholasampatty - Mallappanur road (MD1174A) including upkeeping for a period of 60 months 01-CRIDP-19-20-I-4534
3) Improvements to Riding Quality at Km.0/2-1/8 and 2/6-5/0 of Gonur - Mallikundam road (using Plastic Waste) including upkeeping for a period of 60 months 01-CRIDP-19-20-I-4538
4) Widening from Single lane to Two lane and Improvements of Approach road to Travellers Bungalow at Mettur at Km.0/150-0/300 including Storm water Drain and Providing Paver Block including upkeeping for a period of 60 months 01-CRIDP-19-20-O-2616
5) Improvements of Kolathur - Alamarthupatty road (via) Kurumbanur at Km.3/4-4/6 and 6/0-7/4 including Dip Raising at Km.5/10 & 6/2, Construction of Retaining Wall Km.5/10, 6/2 & 7/4 and Reconstruction of Box Culvert at Km.5/10, 6/2 & 6/4 including upkeeping for a period of 60 months 01-CRDIP-19-20-P-3669
6) Improvements of Kolathur - Thinnapatty road at Km.5/4-7/0 including upkeeping for a period of 60 months 01-CRDIP-19-20-O-2627"
TRN :
719199
|
Salem - Tamil Nadu
Contract Value :
6.04 Crore |Agency Name :
Highway Department
3314Widening, Improvements and Improvements to Riding Quality to Government Roads including Reconstruction of Culverts, Construction of Storm Water Drain, Retaining wall and providing Paver Blocks and Up keeping for a period of 60 months in Mettur (H) C&M Sub Division (Package-36)
The Following works are involved in this package
1) Improvements of Tholasampatty - Mallappanur road at Km.10/2-13/0 including Curve Widening at Km.12/2 and Construction of Retaining Wall at Km.11/2, 11/6 & 12/4 (MD1174A) including upkeeping for a period of 60 months 01-CRIDP-19-20-M-1320
2) Improvements to Riding Quality at Km.13/0-15/8 of Tholasampatty - Mallappanur road (MD1174A) including upkeeping for a period of 60 months 01-CRIDP-19-20-I-4534
3) Improvements to Riding Quality at Km.0/2-1/8 and 2/6-5/0 of Gonur - Mallikundam road (using Plastic Waste) including upkeeping for a period of 60 months 01-CRIDP-19-20-I-4538
4) Widening from Single lane to Two lane and Improvements of Approach road to Travellers Bungalow at Mettur at Km.0/150-0/300 including Storm water Drain and Providing Paver Block including upkeeping for a period of 60 months 01-CRIDP-19-20-O-2616
5) Improvements of Kolathur - Alamarthupatty road (via) Kurumbanur at Km.3/4-4/6 and 6/0-7/4 including Dip Raising at Km.5/10 & 6/2, Construction of Retaining Wall Km.5/10, 6/2 & 7/4 and Reconstruction of Box Culvert at Km.5/10, 6/2 & 6/4 including upkeeping for a period of 60 months 01-CRDIP-19-20-P-3669
6) Improvements of Kolathur - Thinnapatty road at Km.5/4-7/0 including upkeeping for a period of 60 months 01-CRDIP-19-20-O-2627"
TRN :
719200
|
Salem - Tamil Nadu
Contract Value :
6.04 Crore |Agency Name :
Highway Department
3315PACKAGE–37, Widening, Strengthening, Improvements, Construction of Retaining wall including up keeping for a period of 60 months in Govt. Roads in respect of Pattukkottai (H), C&M Subdivision.
Road A, 01-CRIDP-19-20-O-2425-, Widening from Single lane to Intermediate lane and Improvements of Nattusalai-Thuvaranguruchi road at km 4/0-6/0 including upkeeping for a period of 60 months
Road B, 01-CRIDP-19-20-O-2426-, Widening from Single lane to Intermediate lane and Improvements of Nattusalai-Thuvaranguruchi road at km 6/0-7/0 including construction of Retaining wall at Km 6/2,6/4 including upkeeping for a period of 60 months
Road C, 01-CRIDP-19-20-O-2397-,Widening from Single lane to Intermediate lane and Strengthening of Nattusalai-Thuvaranguruchi road at km 0/0-2/0 including upkeeping for a period of 60 months
Road D, 01-CRIDP-19-20-O-2440-, Improvements of Vadiyakkadu-Kalyanaodai road at km 4/0-7/4 including upkeeping for a period of 60 months
Road E, 01-CRIDP-19-20-O-2441-, Improvements of Kumbakonam - Mannarkudy - Adirampattinam road KM 50/4 to Thirumakkottai road at km0/0 -2/0 including upkeeping for a period of 60 months
"
TRN :
676804
|
Trichy - Tamil Nadu
Contract Value :
6.24 Crore |Agency Name :
Highway Department
3316Widening and Improvements to Government Roads including Construction of CD works, Retaining wall and Providing RCC centre median and Up keeping for a period of 60 months in Mettur (H) C&M Sub Division (Package-34)
The Following works are involved in this package
1) Widening from Three lane to Four lane and Improvements of Thermal Power Plant road at Km.2/0-2/4, including Construction of Retaining Wall at Km.2/2 and Providing RCC Centre Median (SH-158) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0366)
2) Widening from Three lane to Four lane and Improvements of Thermal Power Plant road at Km.2/4-2/8, including Construction of Retaining Wall at Km.2/6 & 2/8, Widening of Pipe Culvert at Km.2/8 and Providing RCC Centre Median (SH-158) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0367)
3) Widening from Three lane to Four lane and Improvements of Thermal Power Plant road at Km.2/8-3/2, including Construction of Retaining Wall and Widening of Slab culvert at Km.2/10 and Providing RCC Centre Median (SH-158) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0370)
4) Widening from Three lane to Four lane and Improvements of Thermal Power Plant road at Km.3/2-3/8, including Widening of Slab culvert at Km.3/6 and Providing RCC Centre Median (SH-158) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0368)
5) Widening from Three lane to Four lane and Improvements of Thermal Power Plant road at Km.3/8-4/2, including Construction of Retaining Wall Km.4/2, Reconstruction of Box culvert at Km.3/10 and Providing RCC Centre Median (SH-158) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0369)"
TRN :
719203
|
Salem - Tamil Nadu
Contract Value :
7.49 Crore |Agency Name :
Highway Department
3317Special Repairs to Government Roads in Attur C&M Sub Division (Package-78 )
The Following works are involved in this package
1. Special Repairs to Periyapakkalam - Mayampadi Road KM 1/0 - 4/2 (ODR OSA061)
2. Special Repairs to Thammampatty - Palakadu Road KM 4/6-7/660 (ODR-OSA055)
3. Special Repairs to Periyapakkalam - Mayampadi Road KM 6/0-7/350 (ODR OSA061)
4. Special Repairs to Top Sengattupatty - Periyanagur road Km. 0/0- 0/4 (ODR-OSA003)"
TRN :
733474
|
Salem - Tamil Nadu
Contract Value :
1.18 Crore |Agency Name :
Highway Department
3319Widening and Improvements to Government Roads including Reconstruction of Box culvert, Construction of Storm water Drain, Retaining wall and Well Protective wall and Up keeping for a period of 60 months in Omalur (H) C&M Sub Division (Package-30)
The Following works are involved in this package
1) Construction of drain at km 3/6- 3/8 and 5/2- 5/6 of Tholasampatty road (01-CRIDP-19-20-M-1322)
2) Improvements of M.Chettipatty –Palikadai road at km.0/0- 3/0 including upkeeping for a period of 60 months (01-CRIDP-19-20-O-2626)
3) Improvements of Amarakundhi- Mallikuttai- Olaipatti road at km. 4/0- 6/430 including Construction of Retaining wall at km. 5/4- 6/2 and Reconstruction of Box culvert at km.5/8 including upkeeping for period of 60 months (01-CRIDP-19-20-O-2625)
4) Improvements of Reddipatty – Tholasmpatty road at km 0/0-5/700 including Dip Raising at km. 1/4- 1/6 and Consrtruction of Retaining Wall at km. 2/0- 2/6 and
Construction of Well protective wall at km.1/4(L/s) including upkeeping for a period of 60 months (01-CRIDP-19-20-O-2622)
5) Construction of Drain at km 1/4- 1/8 of Omalur - Sankari road to Amarakundhi (via) Reddipatty , Ammankovilpatty road.(01-CRIDP-19-20-O-2634)
6) Widening from Intermediate lane to Two lane and Improvements of Omalur-Mecheri road to Thindamangalam road at km 0/0 - 1/6 including
Dip raising at km.0/8 and Construction of Retaining Wall at km. 0/10 , Construction of Well protective wall at km.2/8 including upkeeping for a period of 60 months (01-CRIDP-19-20-O-2617)
7) Construction of Drain at km 0/0- 0/8 of Omalur- Mecheri road to Thindamangalam road including
Reconstruction of Box culvert at km.0/2(i), 0/2(ii), 0/4, 0/6, 0/8, 0/10, 1/6, 1/8 (01-CRIDP-19-20-O-2642)"
TRN :
720191
|
Salem - Tamil Nadu
Contract Value :
6.62 Crore |Agency Name :
Highway Department